Emcore Corporation
A Case Study in Hyper-Fast Track Performance at —Gallium Alley“
Background
Emcore is a high-technology company which has recently gone
public. Located on —Gallium Alley,“ the East Coast‘s response to
Silicone Valley, this high profile manufacturer of semi-conductors
specializes in chips that are nano-seconds faster than silicone-
based devices. Building on its recent successes, Emcore planned
to add a cleanroom facility for the manufacturing and testing of
new semiconductors.
The need to get into production quickly required Emcore to part-
ner with a rapid-response organization which would enable them
to quickly produce product to stringent cleanroom specification.
Logging On With Monsen
The Emcore team, which has recently partnered with Monsen Engineering Company on its
Pegasus cleanroom facility, knew the Design/Construct method was ideally suited to the computer
industry, where speed is of the essence. With one company taking single source accountability,
Emcore was enroute to ontime completion.
The Challenges
- Emcore was putting the new facility into an existing, occupied building with only one outside wall.
- Space was tight! In fact, no floor space could be allotted to mechanical equipment.
- The cleanroom zones have precise temperature and humidity control requirements. One 500
square foot room is a class 10 non-destructive testing lab.
- —Up“ time was critical. Emcore manufactures 24 hours a day, seven days a week.
The charge to Monsen was to finish the job, with minimal disruption to the on-site staff, in very short
order, complete with critical backup systems and without taking up any valuable floor space or dis-
rupting adjacent ongoing activities.
The Monsen Program
High, high-tech: Fortunately, there were no restrictions about using the roof. However, to put all
mechanical equipment there, Monsen needed to first reinforce it with structural steel. This need-
ed to be done from inside the operating building. Next, Monsen expanded existing machine room
square footage by building a mezzanine. This was an exacting task, requiring that the mezzanine
be watertight to protect the cleanroom below.
The Hardware
-
240 ton air cooled chiller to serve HVAC and process cooling
loads.
-
Two air handling units: one for the class 1000 manufacturing
area, one for the testing area.
-
All electric switch gear and transformers, usually
housed internally, were designed for placement on
the roof.
Raised floor; HEPA filtration;
Class 1000 testing
Roof mounted mechanical
and support equipment, cre-
ates precious manufacturing
floor space
pg_0002
-
Emergency Generator.
-
All exhaust fans for the manufacturing process, including complete
redundant systems with backup in case of power failure.
power failure.
-
A complete cleanroom suite with class 10 levels and class 1000 rooms and support suites.
The Monsen team worked weekends and 10 hour shifts to minimize disruption to building occupants and coordinate
all sub-contractors, keeping everyone on track to meet Emcore‘s deadline.
A Forty-Alarm Response
Monsen equipped Emcore with 40 alarms at three different levels. This comprehensive automation system assures
critical temperature and humidity levels will be maintained and, if equipment should go down, there will be ample
warning.
Level one
: This type of alarm indicates a problem which does not
impact operation; Monsen dispatches a technician the next business
day.
Level two
: This alarm requires Monsen to log on immediately, through
a modem, to troubleshoot on the computer. A technician will be dis-
patched, if necessary.
Level three
: This type of alarm is reserved for situations where a per-
son must be dispatched immediately. If ignored, level three problems
have the potential to shut down the manufacturing process day or night.
User Friendly Results
Cost of Project
: 2.8 Million
Project Duration
: 18 weeks, including the design and construction
Emcore‘s new facility enabled it to rapidly expand one of its product lines.
Emcore has signed on with Monsen for a Total Care Maintenance agreement, which includes monthly monitoring
of all operational parameters by the Monsen Team.
Monsen‘s professional assurance includes ongoing engineering, monitoring and maintaining of the project to assure
it will remain as fully effective and operational as the day it was installed.
Andover Infinity DDC Controls
24 by 7 by 365: Watchdog
Above
: Code compliant exhaust systems
controlled remotely
Right
: Required structural steel to support
mechanical systems
Monsen Engineering Company
6 Daniel Road East
Fairfield, New Jersey 07004
888-226-6736
www.monsen.com