44 CONTRACTING BUSINESS
DECEMBER 2003
By Mike Murphy,
editor-in-chief
ow to best air condition an
old world, 10-story struc-
ture with a system that de-
livers exceptional comfort,
air quality, and efficiency, while re-
maining virtually inaudible and in-
visible to visitors. That was the
dilemma faced by Ted Dec, the direc-
tor of facilities of perhaps the most
majestic Cathedral in North America
— Cathedral Basilica of the Sacred
Heart, a National Historic Landmark
in Newark, NJ.
It’s not uncommon for HVAC
contractors to encounter challeng-
ing requirements when dealing
with historic landmark buildings.
The concept for a new Cathedral
church was first proposed in 1859.
The colossal construction task be-
gan with the first spadeful of soil
turned in 1898 and culminated in its
dedication on October 19, 1954. It
had been described as a fitting
monument to faith.
Nearly 100 years in planning and
construction — the Cathedral cer-
tainly was an example of faith if there
ever was one. More than stone and
mortar, more than multicolored glass
and delicate woodcarving, this re-
vered church is a majestic monument
of beauty and faith. However, with
inside temperatures sometimes
reaching 100F, and with the need to
preserve a delicate, museum-like in-
terior, it was time to finally air condi-
tion the revered old structure.
Enter Monsen Engineering
The Archdiocese of Newark called
upon Monsen Engineering to per-
RETROFIT/RENOVATION
MORE THAN $500,000
CATEGORY B
Sacred Heart Cathedral Basilica
stands tall in Newark, NJ
pg_0002
DECEMBER 2003
CONTRACTING BUSINESS 45
form an HVAC feasibility study. Mon-
sen’s assessment led to an integrated
solution: a Design/Build approach
which would meet the dual need for
new air conditioning and an upgraded
heating system while enabling the proj-
ect to be completed in less than a year at
a guaranteed price. “The Design/Build
process allowed the project to be com-
pleted within budget and on time,"
says Joe Mistretta, Monsen’s executive
vice president.
Installation Quality
The Cathedral, with its old world
flavor and French Gothic architecture,
was described as a “labor of love, not
of fees and profits" by the first contrac-
tor on the project. So too, Monsen de-
scribes the installation of the new
HVAC system. “Our company is
proud to be preserving this beautiful
landmark," says Patsy Chianca, vice
president of Monsen.
The challenge was getting to the tri-
forium level, some 55 feet high, where
the existing mechanical equipment was
spread over three semi-enclosed areas.
Because the Cathedral was built around
this existing equipment, replacing cer-
tain air handlers was not an option. La-
borious and time-consuming, the in-
stallation included modifying eight
existing air handlers and supplying
each with piping. The air handlers were
renovated with new bearings, shafts,
and variable frequency drives, as were
the two major exhaust fans.
Comfort is Job One
The Cathedral conducts daily
masses and tours, performs weddings
and baptisms, supports a steady
schedule of concerts, and receives visi-
tors from all over the world. Comfort
was determined to be an important el-
ement for providing the right atmos-
phere for prayer and worship. With
temperatures that could soar to 100F
or more, improved temperature, hu-
midity control, and ventilation for the
clergy and visitors were the major
goals in this mission. The innovative
design optimized comfort levels while
minimizing the visual and audible im-
pact of the HVAC system.
Design Quality
The beauty of Design/Build lies in the
up-front planning, which is when an en-
gineering team often discovers that the
normal “run of the mill" equipment so-
lution won’t do. In the case of the Cathe-
dral, the design needed to be functional
while safeguarding the aesthetics and
acoustics of the building. The initial proj-
ect objective was to design an air condi-
tioning system; however, Monsen’s team
discovered during the survey process
that the Cathedral’s heating system and
air distribution system were beyond
their useful life. An air conditioning ad-
dition would overtax the existing sys-
tem, rendering it inoperable. David
Allen, senior project manager says, “The
heating system was over fifty years old
and it wasn’t going to survive in the new
design. The new system needed to pro-
vide both cooling and heating."
As a result, the project was designed
to integrate the heating, cooling, and
ventilation systems, creating a two-
pipe heating/cooling system with a
summer/winter changeover.
The installation required extensive
planning, problem-solving, and team-
work because all of the piping had to be
concealed. Technicians had to bore
through thick concrete and granite
CATEGORY B
Retrofit/Renovation more than $500,000
WINNER AT A GLANCE
COMPANY:
Monsen Engineering, Fairfield, NJ
PROJECT NAME/LOCATION:
Sacred Heart Cathedral Basilica, Newark, NJ
KEY CUSTOMER CONTACT:
Reverend Monsignor Richard F. Groncki
NOMINATION SUBMITTED BY:
Yvette Ludwig
, Monsen Engineering Co.,
Fairfield, NJ
THE PROJECT TEAM:
At Sacred Heart Cathedral Basilica:
¦
Ted Dec, director of facilities
¦
Reverend Monsignor, Richard F. Groncki
At Monsen Engineering:
¦
Joseph Mistretta, P.E., executive vp
¦
Patsy Chianca,vp
¦
James Crabtree, P.E., project manager,
electrical
¦
David Allen, sr. project manager,
mechanical
¦
Joseph Iglar, project manager
¦
Darrell McMannus, project manager.
¦
Charles Tedesco, commissioning
specialist
¦
Peter Flatley, field superintendent
This altar is
made of
Botticini
marble, as
are most of
the eight
chapels
within the
Cathedral.
N
EV
E
R
Underesti-
mate the Wonders of...
pg_0003
The maintenance office is equipped
with a workstation that monitors con-
ditions at the Cathedral. The inte-
grated controls optimize chiller plant
operation and provide valuable data
for the facility engineers. The overall
result is to help conserve energy, re-
duce operating costs, and optimize
comfort.
Energy Efficiency
The project was designed to maxi-
mize savings and reduce maintenance
expenses. The custom-designed air-
cooled chiller consumes 1.24 kW of
electricity per ton of cooling capacity, a
very economic system.
IAQ Improvement
Beyond structural cooling, this
project needed to provide optimal in-
door air quality. To meet the fresh air
requirements mandated by ASHRAE,
the outdoor air ventilation rate was
increased to 15 cfm per person based
on a maximum occupancy of 1,200
people.
Comfort and health were not the only
factors considered in the improvement
of the indoor air quality. The Cathe-
dral’s director of music wanted to stabi-
lize the condition of the church’s valu-
able antique organ. Temperature
fluctuation causes a musical instrument
— such as an organ in a century-old Ca-
thedral — to expand or contract, result-
shafts, even a concrete spiral staircase,
to run vertical piping from the base-
ment all the way up to the triforium
level. “With careful thought, we were
able to find a way to conceal the piping
while maintaining access,"says Joe
Iglar, project manager.
Air distribution was provided by 24
air handlers equipped with variable
frequency drives. The eight existing air
handlers were converted to variable
frequency drives to vary the total air-
flow based upon occupancy.
The new design and installation en-
sured that all HVAC components in
need of regular maintenance are lo-
cated in areas that are accessible.
Quiet On The Outside . . .
The central chiller system needed to
be extraordinarily quiet. It had to meet
the stringent outdoor noise require-
ment set by the New Jersey Noise Con-
trol Regulation Department. Rae Cor-
poration rose to the occasion with its
first ever production of a custom-made
265-ton air-cooled chiller, which
proved to be quieter than the maximum
sound level required by the customer.
Quiet On The Inside . . .
Naturally, the huge and beautifully
adorned place of worship exudes a
quiet interior. To maintain this am-
biance, eight existing air handlers
were completely refurbished to re-
duce air flow levels 50% from the Ca-
thedral’s original system design.
Cooling coils were added to convert
the air handlers to heating/cooling
units. In addition, 16 new air handlers
were added to the design.
Controls
Similar to the equipment dilemma,
the Cathedral had begun to outgrow
its control system. Monsen’s project
team intalled a direct digital control
Trane Tracer system to replace the Ca-
thedral’s original pneumatic system
so that it could also be tied into the
Trane system in the Diocese building.
The digital controls use wireless sen-
sors within the body of the Cathedral.
48 CONTRACTING BUSINESS
DECEMBER 2003
How does one
man hold up a
265-ton air-
cooled chiller.
We don’t know,
but it will disap-
pear if you sur-
round it with a
14-ft. high con-
crete wall and
then finish the
wall to match a
Gothic Cathe-
dral’s granite
exterior.
During summer months, the old system of intake and exhaust fans circulated fresh air
through a network of tunnels and ducts. The obsolete air distribution system wouldn’t
support both heating and cooling within the parameters of the new design.
pg_0004
50 CONTRACTING BUSINESS
DECEMBER 2003
ing in frequent and costly tune-ups. The
new controlled environment will pre-
serve the wood components and sound
quality for the Cathedral’s organ
recitals and annual world-renowned
Christmas concert.
Unique Challenges Resolved
In this project, the emphasis was on
equipment that performs reliably and
unobtrusively. The archdiocesan facil-
ity engineers wanted the chiller in-
stalled in such a way that it wouldn’t
intrude on the eye, the ear, or the land-
scape. After much collaboration, the
air-cooled chiller plant was placed, and
aesthetically enclosed, in a parking lot
near the Archbishop’s residence at the
rear of the Cathedral.
The installation resulted in an in-
visible system, with no mechanical
obstructions inside or outside the Ca-
thedral. The chiller is surrounded by a
custom-built, 14-ft. high concrete en-
closure to hide it from view and re-
duce sound levels. The enclosure is
finished to match the Cathedral’s ex-
isting granite exterior.
Air handlers and fans with quiet
motors and variable frequency drives
reduce noise within the Cathedral.
The installation uses wireless
digital control sensors within the
body of the Cathedral because
hard-wired sensors would affect
aesthetics. The wireless sensors can
communicate with the central com-
puter, and as a backup, the team in-
stalled a hard-wired sensor located
on the triforium level where the
wires are easily hidden.
Design/Build Advantages
The Design/Build format enabled
long-lead equipment to be procured
before all the engineering and permits
were completed. This format also al-
lowed the project to be fast-tracked,
within a year, in phases, to meet
budget constraints and keep the busy
Cathedral operational with no intru-
sion on daily celebrations and special
events.
Thorough Commissioning
Not just an afterthought, commis-
sioning was included as part of the en-
gineering and bidding process. It was
performed throughout the stages of the
project to meet NEBB standards for air
and water balancing.
The project resulted in the newest
and best in HVAC comfort technology,
while preserving the sacred look and
feel of the Cathedral. It’s truly a case of
finding the best of both worlds.
Monsen Engineering has been ex-
ploring and solving the intricacies of in-
door climates for more than 50 years.
This year, a
Contracting Business
De-
sign/Build Award is their reward.
¦
CATEGORY B:
PROJECT-AT-A-GLANCE
Retrofit/Renovation more than $500,000
SYSTEM DESCRIPTION:
Sacred Heart Cathedral Basilica
itself covers an area of
40,000 sq.ft; an area almost equal to that of the famed West-
minster Abbey in London, England. The great church measures
365 ft. in length, with a width of 165 ft. in the transcepts. The front
towers extend 232 ft. into the air, 28 ft. higher than Notre Dame Ca-
thedral in Paris. The HVAC renovation, initially planned to be for
cooling only, resulted in a two-pipe heating/cooling system with
summer/winter changeover.
The installation required extensive planning, problem-solving, and team-
work because all of the piping had to be concealed. Technicians had to bore through
thick concrete and granite shafts — even a spiral staircase — to run vertical piping 55
ft. from the basement up to the triforium level.
The central chiller system needed to be extraordinarily quiet. The design called for a
custom-built nominal 265-ton air-cooled chiller. Eight of the existing air handlers had to
be completely refurbished to reduce air flow to 50% of the original heating design. Cool-
ing coils were added to convert air handlers to heating/cooling units. In addition, 16 new
air handlers were added to the design.
Monsen Engineering, Co.
Some of the unique problems solved:
¦
A complex project was designed and installed within one year at a guaranteed price.
¦
Existing mechanical equipment was spread over three semi-enclosed areas, 55 ft.
high in a triforium level of the church.
¦
The Cathedral had been built around the existing equipment and couldn’t be altered
during the renovation. Space was tight.
¦
Without disturbing the structure, outdoor air ventilation had to be increased.
¦
All equipment were required be hidden from view. Chiller installation was not to
intrude on “the eye, ear, or landscape."
¦
One requirement was that the Cathedral must remain operational with no intrusion
on daily celebrations and special events.
PRODUCTS KEY TO SUCCESS
¦
Air-cooled Chiller — Rae Corporation
¦
Air Handlers— Trane
¦
Control System — Trane
¦
Heat Exchanger — Armstrong
¦
Variable Frequency Drive — ABB
¦
Glycol Pumps — Armstrong
The chiller was lifted into place after a pad
had been prepared and all glycol piping
run to the Cathedral. Total construction
time was less than one year.
RETROFIT/RENOVATION
MORE THAN $500,000
CATEGORY B